June Construction Update: Stage 1 Construction Milestones

Traders In Purple is very excited to share a number of significant construction milestones at Lasail Newport.

Most significantly, the joinery is now fully installed up to level 4, including benchtops. The installation of appliances complete on level 1 and continuing to progress on upper levels.

Internal works are advancing on level 5, with painting and internal linings continuing. All internal framing now complete to level 6 the installation of internal linings are progressing.The pool villa roofs are on, and townhomes structural works are nearing completion.

The scaffold drop has commenced, giving the first glimpse of the building façade.

Meanwhile, on Stage 2 the final slab for Level 2 was poured on Monday, with formwork for Level 3 advancing ahead of the first pour later this month.