July Construction Update: Stage 2 Construction Milestones

Traders In Purple is excited to share a number of significant construction milestones at Lasail Newport.

Stage 2 formwork on level 1 has been stripped ahead of the window and fire wall installation. Structures to level 4 are well underway, following the final pour of the Level 3 slab.

Stage 1 works are progressing well as we near closer to completion. Internally, the joinery and stone installation is now complete up to level 4.

On the podium, the resident’s recreation area is beginning to take shape with the construction of the pool, BBQ area and garden bed structures progressing.

The scaffold drop will continue over the coming weeks, revealing more of Lasail Port’s façade.