May 20, 2022
Stage 2 has hit several significant milestones this month, including the completion of in-ground service works.
Our team is now advancing with the final 2 concrete slab pours on level 1, which is expected to be completed by the end of the week.
Stage 2 is also continuing its vertical ascent with structural elements now reaching level 2, while 50% of formwork slabs anticipated for completion mid-May.
Construction to pool villa's in Stage 1 have commenced and 50% of structural works to townhomes completed.