February 2, 2022
Marking an exciting milestone, the construction has commenced with preliminary site works and piling for Stage 2 fast-tracked. Piling is expected to take approximately 2 weeks and will be followed by the formwork for the level 1 slab pour.
Stage 1 structural works continue to progress with the level 4 slab complete and formwork for Level 5 underway. Meanwhile, on Level 1 the apartments are beginning to take shape with all internal frames and services rough-in now complete.