Construction update: Stage 1 Nearing Top Out

March 30, 2022

Despite significant rainfall, we are nearing an exciting milestone with the roof pours of Stage 1 now underway, we expect to top out early April, weather permitting.

The internal fit out continues to progress on level 1 with the first coat of paint applied and internal tiling complete, the kitchen and robe installs are underway. While sheeting is complete and tiling is underway on level 2, the installation of firewalls and services rough-ins are progressing on the upper levels as scheduled.

We will soon see the townhomes begin to take shape with the installation of in ground services now finalised, and 50% of foundations complete.

The preliminary inground works of Stage 2 are well underway. We expect all inground footings and services to be complete at the end of this month, with the first slab pours to follow shortly.