November 2, 2021
Marking another milestone, the construction team have now completed the structure for all of Level 1 and Level 2 of Lasail Port. Structural works continue to progress in preparation for the Level 3 slab pour later this month.
For those interested in the details:
- All in-ground services for Lasail Port are complete
- Level 1 slabs complete, and formwork stripped and back propped
- Level 2 slabs and carpark for Lasail Port are complete
- While Level 2 to 3 vertical walls and structural cores are 50% complete ahead of Level 3 slab pours to commence later this month